Arden, NC Traffic and Road Conditions

 
Click any alert icons on the map to see info.

Arden Traffic Alerts

3464
Road Closed on SR-3464 West of Asheville
Bridge #100434 in Buncombe County on SR 3464 (Black Oak Cove Rd) will be replaced by a new structure.  SR 3464 (Black Oak Cove Rd) will be closed and an off-site detour will be put in place while the structure is replaced.  The project is under contract with NHM Constructors and will finish late fall of this year.
DETOUR: Follow Detour Signs
Start: June 19, 2017, 11:00 am / End:November 15, 2017, 10:00 pm / Updated: June 16, 2017, 7:41 pm
1397
Lane Closed on SR-1397 North West of Weaverville
Bridge #100677 in Buncombe County on SR 1397 (Surrett Cove Rd) will be replaced by a new structure.  SR 1397 (Surrett Cove Rd) will be closed and an on-site detour will be put in place to a one lane one way pattern utilizing a flagging operation while the structure is replaced.  The project is under contract with Dane Constructors and will finish early winter of this year.  
Start: April 12, 2017, 11:00 am / End:December 8, 2017, 10:00 pm / Updated: April 4, 2017, 1:30 pm
1103
Road Closed on SR-1103 West of Asheville
Buncombe Bridge #555 on SR 1103 (Davis Creek Rd.) will be replaced by a new structure.  SR 1103 (Davis Creek Rd.) will be closed between SR 1105 (Brooks Cove Rd.) and SR 1106 (Bens Cove Rd.) while the structure is being replaced.  The road will be closed starting in July and continuing until early winter, but an off-site detour will be set up to help maintain traffic.  The project is under contract with NHM Constructors. 
DETOUR: Follow Detours Signs
Start: July 21, 2017, 11:00 am / End:November 15, 2017, 10:00 pm / Updated: July 20, 2017, 2:18 pm
63
Congestion on NC-63 North West of Asheville
Construction on NC 63 (New Leicester Hwy) from SR 1516 (Gilbert Road) to SR 1004 (Newfound Road). The construction is for widening and other improvements. There will be temporary lane closures at times as needed. The project is under contract with Tennoca Construction Company.
Start: December 1, 2016, 5:00 am / End:July 1, 2020, 4:00 am / Updated: May 16, 2017, 5:52 pm
280
Lane Closed on NC-280 South of Asheville
NC 280 (Airport Rd) will have a nightly lane closure starting at 7:00pm due to a sidewalk installation project. The project limits are from Birch Circle (Walmart's entrance/exit) to SR 3568 (Rockwood Rd). The project is under contract with Cooper Construction Company.
Start: July 24, 2017, 11:00 pm / End:November 17, 2017, 5:00 am / Updated: July 26, 2017, 1:26 pm
191
Lane Closed on NC-191 South of Asheville
NC 191 (Brevard Rd.) will have lane closures in both the north and soundbound directions while crews remove concrete islands.  Lane closures will start at Pine Lane and continue until Pacoda Street on NC 191.  Construction will start Monday night at 7:00 pm and continue throughout the rest of the week.  The project is under contract with Blythe Development.
Start: October 16, 2017, 11:00 pm / End:October 21, 2017, 10:00 am / Updated: October 16, 2017, 7:36 pm
26
Lane Closed on I-26 South of Asheville
I-26 between MM 31 and 37 will be reduced to one lane in both the east and westbound directions while crews do asphalt paving. Construction will be on Sunday night between the hours of 7:00 pm and 6:00 am and continue throughout the week. The project is under contract with Blythe Development.
Start: October 15, 2017, 11:00 pm / End:October 20, 2017, 10:00 am / Updated: October 15, 2017, 4:59 pm
26
Lanes Narrowed on I-26 South West of Asheville
I-26 Eastbound will be under construction as the ramp connecting I-26 Eastbound from I-40 Eastbound is being extended. The contractor will shift traffic slightly while the work is being performed and reduce lane size. The contractor will set barrier rail to protect the work area. Work will be performed starting 8/15 at appromixately 7:00 PM. The project is under contract with NHM Constructors.
Start: August 15, 2017, 11:00 pm / End:November 20, 2017, 5:00 am / Updated: August 16, 2017, 8:23 pm
26
Lane Closed on I-26 Near Weaverville
I-26 will have some bridge rehabilitaition work, guardrail maintenance/construction, and asphalt paving throughout the life of the project. One lane in each direction may be closed at a time for these activities. Work will typically take place during the days Monday through Friday with occasional weekend and night work.
Start: September 27, 2017, 12:00 pm / End:July 31, 2018, 9:00 pm / Updated: September 26, 2017, 8:44 pm
source: North Carolina DOT


NCDOT on Twitter

twitter icon

Visiting the Wings of Freedom tour at RDU this week? Know how to go & where to park: https://t.co/wZHNz5z8bW #WingsOfFreedomRDU

Oct 17, 2017, 11:34 am EDT replyretweetfavorite
twitter icon

@Chris_Travels This project began last month on major interstates throughout NC and will continue through Nov. 2018… https://t.co/FOVziyGWLm

Oct 17, 2017, 8:22 am EDT replyretweetfavorite

Traffic Nearby

More Local Information

Bookmark and Share

Arden weather and traffic updates by locals

Write your own Arden, North Carolina report, forecast, or traffic update:

Please note by clicking on "Post" you acknowledge that you have read the Terms of Service and the Arden, NC report and/or forecast you are posting is in compliance with such terms. Be respectful. An inappropriate Arden, NC report and/or forecast will be removed by a moderator.